Proposed Schedule:
Carlsbad Energy Center Project (07-AFC-6)

EVENT
 
DATE

Applicant files Application for Certification (AFC)
9/14/07

Executive Director's recommendation on data adequacy 10/12/07

Decision on data adequacy at the business meeting
10/31/07

Staff files Issue Indentification Report
12/10/07

Information hearing and site visit
12/17/07

Applicant provides data responses
12/21/07

Data request/response and issue resolution workshop
1/24/08

Data request/response and issue resolution workshop #2
3/26/08

Local, state and federal agency draft determinations & SDAPCD PDOC
10/24/08

Preliminary Staff Assessment (PSA) Completed 12/12/08

PSA Workshops
1/7/09 & 1/8/09

Local, state and federal agency final determinations & SDAPCD PDOC
1/30/09 according to new CEC Staff Schedule

Staff files final Staff Assessment
1/30/09 according to new CEC Staff Schedule

Evidentiary hearings* 2/1/10 - 2/4/10

Committee files proposed decision* TBD

Hearing on the proposed decision* TBD

Committee files revised proposed decision* TBD

Commission Decision TBD

* The CEC will determine this part of the schedule

 